Client: City of Charleston, SC
       Consulting Engineer: Davis &  Floyd/URS
       Construction Manager: Black &  Veatch
       Contractor’s Consulting Engineer:  ARUP
Contract Amount: $16,700,000
Scope: 4,000 LF of 108” monolithic concrete  in tunnel.
Access Shaft: One 20 foot diameter  access shaft, 140 feet deep installed by sunken caisson  method. 54”
Drop Shafts: Three 54”  diameter drilled drop shafts.
Overflow structure and pipe: 54” overflow sewer connecting to a precast overflow outlet structure.
Tunnel Pump Station Connection:  Tunnel connection to the Concord Street live wet well and pump station.
     Triad Midwest Mole JV, a joint  venture of Triad and Midwest Mole, Indianapolis, Indiana recently completed the  Market Street Drainage Tunnel in downtown Charleston, SC. Triad was the managing partner of the JV. 
     This high profile project included a  number of unique challenges:
     
       - Two tunnels were to be installed from  one access shaft to one dead end and one live pump station. There was no outlet  for the tunnel excavation equipment. The tunneling machine (TBM) was required  to be removed from the initial access or starting shaft. 
- The original downstream tunnel outlet  was to be a connection into an existing live tunnel. 
- The tunnel was to be excavated by  Sequential Excavation Methods, TBM with precast segments or by contractor  design (by contractor’s consulting engineer) approved by the owner. Triad  Midwest Mole submitted its own two stage, tunnel design which included TBM  excavation using ribs and boards followed by the installation of a monolithic  concrete lining. 
- Three drilled drop shaft connections  were to be installed in the Charleston Market area (on Market Street). The  drill drops were in very tight, congested, tourist filled areas either adjacent  to or between two market buildings. 
- The access shaft site was very small  and immediately adjacent to Charleston’s cruise ship dock. 
- The Concord Street leg of the tunnel  system was to be excavated downhill at a very steep grade(2.6%) to the live  tunnel connection. 
- Ground Freezing was required in the  zone of the live tunnel connection. 
Large  problem discovered
       The  project required initial vertical probe drilling along the Concord Tunnel  alignment to verify that the new tunnel would not encounter the old abandoned  Charleston Water System sanitary sewer tunnel. The old tunnel was full of water  and subject to the hydraulic head produced by the Cooper River/Atlantic  Ocean.  The probe drilling revealed that  a zone of the original CWS tunnel crown had failed and expanded outward  directly into the new tunnel zone.  
     Solution
       Triad  Midwest Mole engineers in coordination with their outside consultant ARUP  redesigned the project. The following changes and solutions were made:
  
       - The tunnel depth at the access shaft  was lowered to 140 feet from its original 83 feet. That change lowered both  tunnel runs to a safe depth below the abandoned CWS tunnels. This eliminated  any risk of intrusion from the old tunnels. The resultant tunnel grades were at  a much flatter gradient, eliminating the original steep downhill grade and  providing much safer working conditions. 
- The tunnel outlet was moved from the  original connection point on the East Bay Calhoun tunnel to a direct connection  with the wet well of the Concord Street Pump Station. This was accomplished by  the rerouting of the Concord tunnel from a straight line into an S curve which  ended at the wet well. 
      The access shaft was installed by the sunken caisson method.